Cascading problems after Kendal coal conveyor belt broke led to Stage 4

2022-09-17 03:34:55 By : Ms. Holly Hou

Note: Search is limited to the most recent 250 articles. To access earlier articles, click Advanced Search and set an earlier date range. To search for a term containing the '&' symbol, click Advanced Search and use the 'search headings' and/or 'in first paragraph' options.

Please enter the email address that you used to subscribe on Engineering News. Your password will be sent to this address.

separate emails by commas, maximum limit of 4 addresses

Cascading problems after Kendal coal conveyor belt broke led to Stage 4

Embed VideoPopup VideoInstagram

13th September 2022 By: News24Wire

SAVE THIS ARTICLE      EMAIL THIS ARTICLE

Eskom had to jump to Stage 4 load-shedding on Tuesday morning after a coal conveyor belt broke at Kendal, leading to cascading problems and the failure of three units at the power station. 

"In the early hours of this morning a conveyor belt feeding coal into Kendal Power Station failed. To conserve coal, the power output of the generators was reduced, but this required fuel oil to be used to sustain the boiler combustion," Eskom said in a statement. 

"Subsequently, the fuel oil plant supplying the units experienced a failure and shut down. This resulted in the trip of the three generating units. The Kendal units are anticipated to return to service by the weekend." 

Before this a generating unit each at Arnot and Medupi power stations had been taken offline for emergency repairs.

Eskom said there has been "intense" use of its pumped storage schemes and open cycle gas turbines to fill the generation gap due to the breakdowns. 

"While some generation units are anticipated to return to service over the next 24 hours, it is necessary to increase the load shedding to conserve the emergency reserves." 

Eskom said that 5 446 MW is out on planned maintenance, while another 16 985 MW of capacity is unavailable due to breakdowns.

Stage 4 started at 10:00 on Tuesday and is expected to last until 05:00 on Thursday morning. After that it will be lowered to Stage 2 until midnight on Friday. 

Edited by: News24Wire EMAIL THIS ARTICLE      SAVE THIS ARTICLE

To subscribe email subscriptions@creamermedia.co.za or click here To advertise email advertising@creamermedia.co.za or click here

Engineering News is a product of Creamer Media. www.creamermedia.co.za

Other Creamer Media Products include: Mining Weekly
Research Channel Africa Polity

Sign up for our FREE daily email newsletter Receive daily sector news alerts

We offer a variety of subscriptions to our Magazine, Website, PDF Reports and our photo library.

Subscriptions are available via the Creamer Media Store.

Advertising on Engineering News is an effective way to build and consolidate a company's profile among clients and prospective clients. Email advertising@creamermedia.co.za